Tehran-Shomal Highway - Slowly But Surely!

17 June, 2019 14:56

Mr. Nobakht –President Deputy and Head of Planning and Budget Organization of I. R. Iran has paid a visit to Tehran-Shomal Highway Project. He promised that the required budget (amounting to Euro 40,000,000) will be arranged in order to complete the Phase One, by the end of 2019.  Managing Director of Tehran-Shomal Highway Company, attending the visit, also emphasized on his support to achieve the mentioned target.

Recently following materials have been arrived in Tehran-Shomal Project:

  • Road Compact Panels (16 Panels),
  • Main Tunnels Lighting Panels,
  • Fire Alarm System for all main tunnels and buildings,

Other ongoing activities:

  • Sample of Fire Box on Tunnels 16 has been installed and approved for production,
  • Cable Laying of ducts and trays are ongoing,
  • Financial impediments and issues are being regularly discussed with client,
  • Control Room of Tunnels 13 and 14/15 is under final civil work and expected to be ready for installation of Control System latest by July 10th 2019.

 

 

 